Rehabilitation of Runway and Taxiway, Extension of Box Culvert and Ancillary works at Asaba International Airport, Delta State, Nigeria


Brief Description

This project consists of—

·      The rehabilitation of 3.4 km (45 m + 2 x 7.5 m width shoulders) failed section of Runway,

·      The rehabilitation of failed section of Taxiway (25 m +2 x 17.5 m width shoulders),

·      Correction of existing Bumpy profile, overlay of existing Runway and Taxiway, ramping of edges,

·      Construction of subsurface drains across the Taxiways,

·      Construction of crash road for Runway at both ends,

·      The grading of Runway strip and construction of parallel trapezoidal earth drain,

·      Extended of Box culvert (80 m) and others associated concrete works,

·      Blast Pad at Runway 29 End (60m x 45m),

·      Fire station roads and others associated works,

·      Pavement Markings and

·      Signage & Safety Measures. 


Client: Delta State Ministry of Works, Asaba

Contract Awarded: December 2017

Project Status: Completed